General Update
Night time work is expected from from time-to-time during commissioning activities until the end of December 2024.
November 2024
Clearview Solar is nearing completion of major construction activities.
The Project is undergoing final commissioning activities.
Clearview Solar anticipates that the project will begin facility operations on or around December 23, 2024.
Commercial operation is anticipated to be around February 28, 2025.
October 2024
Deliveries
100% of modules delivered to date.
Civil
Mowing & seeding activities ongoing.
95% of the project site has been mowed to date.
Chemical spraying of approved herbicide commenced 10/15/24. All exterior locations have been sprayed with an approved herbicide application. Array spraying commenced on-site 10/23/24.
Structural
Piles is 100% complete.
Racking is 100% complete.
Electrical
Module installation is 100% complete.
DC Harness 98% complete.
DC Terminations 89% complete.
Feeder Install 96% complete.
DC Mod to Mod 100% complete.
DC String Wire 100% complete.
DC AWM 97% complete.
Substation
Substation commissioning 99% complete.
Construction for the substation 100% complete.
Commissioning
Self-perform commissioning activities are currently ongoing. Overall, commissioning is 75% complete.
August 2024
Deliveries
100% of modules delivered to date.
Civil
Drain Tile Reroutes 100% complete.
Mowing & seeding activities ongoing.
Structural
Pile installation ongoing. 99% of array piles driven.
97% of racking complete.
Electrical
Module installation is ongoing. 94% modules installed.
Substation
Substation commissioning 99% complete.
Construction for the substation 100% complete.
May 2024
Deliveries
Module deliveries ongoing.
Current schedule 35 trucks/week.56% of modules delivered to date.
Civil
1 of 2 planned HDD bores complete.
Mowing & seeding activities as part of site remediation efforts ongoing.
Structural
97% of array piles driven.
Finish racking and racking QC crews are active west of Snapptown Rd snaking northbound. Rough racking has begun in the middle portion of the project between Snapptown Rd and Indian Creek snaking southbound.
Electrical
Module installation is ongoing. 45% modules installed.
Substation
Substation EPC has mobilized. Substation activities include structural steel install. Main power transformer was delivered and installed.
April 2024
Deliveries
Module deliveries ongoing.
Civil
Work on Bores is on-going.
Perimeter fence installation complete, apart from gates.
Permanent seeding work is active.
Structural
Pile driving activities continue.
Racking work continues.
March 2024
Deliveries
• Module deliveries scheduled for March, 2024.
• Pile deliveries are nearing completion.
• Racking Deliveries are complete.
Civil
Work on Bores is on-going.
Perimeter fence installation complete, apart from gates.
Permanent seeding work is active.
Structural
Pile driving activities continue.
Racking work continues.
February, 2024 Update
Deliveries
• Inverter deliveries are on-going.
• Module deliveries scheduled for March, 2024.
• Pile deliveries are nearing completion.
• Racking deliveries are nearing completion.
• Straw mulch deliveries continues.
Civil
Work on Bores is on-going.
Perimeter fence installation continues.
Mulching work is active.
Structural
Pile driving activities continue.
Racking work continues.
January, 2024 Update
Deliveries
Module deliveries scheduled for March, 2024.
Inverter deliveries scheduled for February - March, 2024
Civil
Work on Bores is on-going.
Perimeter fence installation continues.
Mulching work is active.
Structural
Pile driving activities continue.
Racking work continues.
General Update
PCL will begin general construction activities from 7 am to 5 pm, Monday to Sunday starting on 1/6/2024. Pile driving activities will continue to not commence until 9 am daily.
December, 2023 Update
Deliveries
Pile deliveries ongoing throughout this period.
Racking and tracker deliveries are ongoing throughout this period.
Fiber, ground wire, and AC deliveries are complete.
DC cable deliveries ongoing.
Inverter deliveries scheduled for February 2024
Civil
Work on Bores is on-going.
Perimeter fence installation continues.
Structural
Pile driving activities continue.
Racking work continues.
November, 2023 Update
Survey
Surveyors have been on site since mobilization, and their work is ongoing.
Deliveries
Pile deliveries ongoing throughout this period.
Racking and tracker deliveries are ongoing throughout this period.
Fiber, ground wire, and AC deliveries are complete.
DC cable deliveries ongoing.
Drain tile material deliveries complete.
Inverter deliveries scheduled for February 2024
Civil
Interior project roads complete. SILT fence installation is complete.
Perimeter fence subcontractor mobilized during this period.
Structural
Pile driving activities continue.
Inverter pile foundations complete.
Torque tubes and racking continues.
Racking work continues.
October, 2023 Update
Survey
Surveyors have been on site since mobilization, and their work is ongoing.
Deliveries
Pile deliveries ongoing throughout this period.
Racking and tracker deliveries are ongoing throughout this period.
Civil
Interior project roads complete. SILT fence installation is complete.
Perimeter fence subcontractor mobilized during this period.
Structural
Pile driving activities continue.
Inverter pile foundations complete.
Torque tubes and racking continues.
Electrical
Grounding inverter skid complete.
September, 2023 Update
Survey
Surveyors on site, work is ongoing throughout the project footprint.
Deliveries
Pile deliveries ongoing.
Racking hardware deliveries is ongoing throughout this period.
Wire deliveries is ongoing and nearly complete.
Civil
Interior project roads complete.
1 of 2 planned HDD bores complete.
Ongoing installation of silt fence and stormwater BMPs.
Structural
Pile driving activities continue.
Inverter pile foundations continue.
Array pile foundations continue.
Electrical
Rough ins and grounding at inverter skids continue.
MV junction box installation work continues.
August, 2023 Update
Survey
Surveyors have been on site since mobilization and their work is ongoing throughout the project footprint.
Deliveries
Pile and racking hardware deliveries are ongoing.
Wire deliveries are on-going.
Civil
Construction of interior project roads and laydown areas is on-going.
Ongoing installation of silt fence and stormwater BMPs according to the SWP3.
Structural
Pile driving activities have commenced with inverter skid foundation piles.
Electrical
Rough ins and grounding at inverter skids on-going.
Other
OPSB and Ohio EPA were on site on August 7th,2023.
Overall reception was positive, and no major issues reported
Notice to Stakeholders
Impact pile driving will be starting at Clearview on July 15th, 2023 for approximately a 4 month period. Pile driving activities will be conducted during the hours of 9 am to 7 pm Monday to Sunday and may be required between 7 am to 9 am from time to time.
July, 2023 Update
PCL started with survey operations on June 14, 2023 and started Mobilization on June 19, 2023. Here are the things currently being worked on:
Site Survey of entrances, laydowns, SWPPP and project limits,
Install of Laydown yards, focused at gate B3
Install of project entrance B3
Start receiving of DC, AC, and Misc. electrical equipment deliveries
Install of access roads, east side of Indian Creek
Install of temporary SWPPP erosion control measures, east side of Indian Creek
June Update
Clearview Solar Construction is anticipated to commence on June 14th, 2023